Current lab priorities: lampoly, p5000etch, drytek4
E-Beam, SEM & Maskmaking
ebeam down following power glitch Monday morning.
raith - up
sem4160 - up
semhitachi - up
Optical Photolithography
Resist Coat
headway2 - up
laurell-R - up
svgcoat/2 up. Intermittent spin and EBR problems reported.
kscoat - down
Exposure
asml up. 3-D align stage upgrade, tentatively scheduled for mid- late- April and will be unavailable for about two weeks. Stay tuned for updates.
evalign up. PM and WEC replacement tentatively scheduled for next week (March 3)
evg-imprint - up
karlsuss up. Resolution not optimal. PM to be scheduled soon.
karlsuss2 up. Resolution not optimal. PM to be scheduled soon.
nikon up. Not used yet in 2008.
ultratech down. For good.
Develop
svgdev/2 Possible develop issue on #2.
Oven Bake & Cure
bluem up.
fusion up. Receiver index issues. Run one wafer at a time.
uvcure up.
yes up.
Chemical Vapor Deposition
Low Pressure CVD
teos2 - up
thermconitride1 up.
thermcopoly1 up.
thermconitride2 down. Under process development.
thermcopoly2 up. Under process development.
tylanbpsg up.
tylannitride up. MFS alarm reported.
tylanpoly up.
tylansige up.
PECVD
sts up.
tel up.
ald - up
epi up. Low p dopant out/on order. Reflector needs replacement.
epi2 up. Handling issues. B-side OK.
Metallization and Sputtering
gryphon up. Intermittent pumping problem reported. To be address with a major, scheduled PM some time in coming weeks (ferrofluidic seal and target replacement). Be aware that base pressure will be higher than usual for a couple of weeks following the PM.
innotec up. Roughing pump not working really well, but as long as it crosses over it should be OK. Pump will be rebuilt or replaced.
metalica up.
sct - up
Dry Etching
amtetcher up. Robin checked etch rates, which look good.
drytek1 up.
drytek2 up.
drytek4 down. Matching network failed. Needs repair.
gasonics up.
lampoly down. Losing wafers and turbo errors. Looking like the turbo backing pump has failed. A spare is due back soon. If all goes well, it should be back up this week. If not, all bets are off.
matrix
mrc
p5000etch up, limping on two RF generators for three chambers. Right now, ChC generator is on ChA. Please coordinate with staff about scheduling RF generators. (Equipment may be unavailable at times this week while maintenance installs and checks a spare generator.)
pquest
pquest2
stsetch up. C4F8 flow problem reported. Process recipe ran for 30 minutes without problem. System remains in yellow for observation.
stsetch2
xactix A leak is suspected. Plans to reinstall gas cylinder.
Annealing, Oxidation, and Doping
Furnaces
fga2 - up
thermco1- up
thermco2- up
thermco3- NA
thermco4- NA
tylan1- up
tylan2- up
tylan3- up
tylan4- up
tylanfga- up
Rapid Thermal Processing
AG4100
AG4108
rtaag
rtagaas
Doping
tylan5- up
tylan6- up
Wet Benches
cpd- up
lithosolv- up
solvhood- up
tubeclean- up
wbdiff- up
wbebres- up
wbgaas- up
wbgeneral- up
wbgen2- up. Clean station, for germanium cleans. Users requiring wafer cassette processing of gold-contaminated materials, contact Mary & Uli.
wbmetal- up
wbmiscres- up
wbnitride- up
wbnonmetal- up
wbsilicide- up
wbsolvent- up
Wafer Bonding & Sawing
cmp- up
evbond- up
ksbonder- up
thermolyne- up
wafersaw- up
Characterization & Testing
alphastep- up
afm2- up
ellipsomter- up
nanospec/2- up
prometrix- up
p2- up
stresstest- up. Intermittent stage home and Z-height problems.
woollam- up
zygo- up. No network connection.
Facilities
- Power glitch Monday morning ~7:30.
- DI water OK. Backup pump is being repaired. Facilities is looking into having all pumps updated and replaced.