Subject: Re: Will be Raith be up on Friday morning? YES! Current PLAN -- system coming back on line 1800 Thursday
From: James Conway <jwc@snf.stanford.edu>
Date: Wed, 05 May 2004 17:14:15 -0700
Wed, 05 May 2004 17:14:15 -0700
Greetings:

Carl Zeiss and RAITH Field Service have just handed the system back to 
me for performance testing and LEO column adjustments evaluation.

  My plan:

   1. Complete beam drift evaluations this afternoon.  Beam drift is
      well within specification (spec. 10 nm/min. measured 3 - 5 nm/min.

   2. Hand off the system to Gigi and other available RAITH champions
      after GiGi overnight and into Thursday morning.

   3. I will return to the system at 10 AM tomorrow and hope to complete
      qualification testing by late tomorrow afternoon.

   4. I hope to release the system back to users at 6 PM tomorrow.

Thank you for your patience and support!

James Conway





Peter Catrysse wrote:

>Hi James:
>
>I am losing two 4-hour time slots next week (I had Tuesday and Thursday
>morning) as a result of the training class you are giving. I reserved some
>time this Friday morning. How realistic is it that you will be done by then?
>
>Thanks,
>
>Peter Catrysse
>
>  
>
>>-----Original Message-----
>>From: James Conway [mailto:jwc@snf.stanford.edu]
>>Sent: Wednesday, May 05, 2004 1:21 PM
>>To: Peter Catrysse; Raith SNF Mailing list; ebeam@snf.stanford.edu
>>Subject: I have a 6 inch wafer HEADWAY chuck you can check out from me for
>>EBeam Lab use.
>>
>>Greetings:
>>
>>I have now obtained a 6 inch wafer chuck for the Headway spin coater.
>>This is to be kept secured at my desk and will need to be check out
>>through me for every loan.
>>
>>Thank you for your support!
>>
>>James Conway
>>
>>    
>>
>
>  
>


Greetings:

Carl Zeiss and RAITH Field Service have just handed the system back to me for performance testing and LEO column adjustments evaluation.

  My plan:

  1. Complete beam drift evaluations this afternoon.  Beam drift is well within specification (spec. 10 nm/min. measured 3 - 5 nm/min.

  2. Hand off the system to Gigi and other available RAITH champions after GiGi overnight and into Thursday morning.

  3. I will return to the system at 10 AM tomorrow and hope to complete qualification testing by late tomorrow afternoon.

  4. I hope to release the system back to users at 6 PM tomorrow.
Thank you for your patience and support!

James Conway





Peter Catrysse wrote:
Hi James:

I am losing two 4-hour time slots next week (I had Tuesday and Thursday
morning) as a result of the training class you are giving. I reserved some
time this Friday morning. How realistic is it that you will be done by then?

Thanks,

Peter Catrysse

  
-----Original Message-----
From: James Conway [mailto:jwc@snf.stanford.edu]
Sent: Wednesday, May 05, 2004 1:21 PM
To: Peter Catrysse; Raith SNF Mailing list; ebeam@snf.stanford.edu
Subject: I have a 6 inch wafer HEADWAY chuck you can check out from me for
EBeam Lab use.

Greetings:

I have now obtained a 6 inch wafer chuck for the Headway spin coater.
This is to be kept secured at my desk and will need to be check out
through me for every loan.

Thank you for your support!

James Conway