Subject: Problem raith SNF 2004-08-28 13:00:07: NO operations above 10 keV
From: jwc@snf.stanford.edu
Date: Sat, 28 Aug 2004 13:00:08 -0700

we wish to allow the FE-gun two weeks of conditioning before we resume regular operations.
 This is to allow the FE-tip to condition itslef and run in properly.
System was tested repeatedly to 30 keV with no EHT trips or vacumm ouotgassing above
normal levels
JWC 08282004:1256 hrs