Subject: Re: Problem raith SNF 2007-10-19 16:04:52: FE-GUN run up in progress.
From: jwc@snf.stanford.edu
Date: Fri, 19 Oct 2007 17:05:48 -0700

full system check out completed.
preliminary qualification write in progress.
FE-Gun will take a day or so to reach deep vacuum and optimal emission levels. 
Ready for next user after 18:00 hours
turbo pump and cooling loop will need flushing and exchange next week. Raith field service
requested... 