Comment cryostation SNF 2012-03-06 11:04:40: Repair Status

hazeghi at snf.stanford.edu hazeghi at snf.stanford.edu
Tue Mar 6 11:04:40 PST 2012


Radiation shield repairs [Completed]
Cool down test [Completed]
DC probe cables + new probe tips on order
Transfer line jacket scheduled for pump down pending arrival of parts
Estimated time of arrival is March 16