From tberg at snf.stanford.edu Wed Dec 1 06:25:37 2004 From: tberg at snf.stanford.edu (Ted Berg) Date: Wed, 01 Dec 2004 06:25:37 -0800 Subject: Diffusion Morning Report 12/01/04 Message-ID: <41ADD461.1060906@snf.stanford.edu> Good Morning All, Happy December to all. Looking pretty good this morning. Poly is back up and Nitride pull and clean is completed and coated- waiting for a test. Had problems with epi- HCl cylinder change. Thermco poly and TEOS2 testing. Everything else looks OK for now. . Date: 12/1/2004 Tube Name/Number Status Comments THICKNESS-Change at Tylan 1 Up Tylan 2 Up Tylan 3 Up Tylan 4 Up Tylan 5-BBr3 Up Tylan 6-POCl3 Up Tylan 7-TEOS2 down Qual testing Tylan 8-SiGe Up 12.88/30 Tylan 9-Poly Up .66/30 Tylan 10-Nitride down pull and clean 0/30 Tylan 11-BPSG-LTO Up 17.56/30 Tylan 12-FGA Up Tystar Up 19.98/30 Doped Poly GONE TEOS up Tylan 16 N/A Thermco 1 Up Thermco 2 Up Thermco Poly yellow testing Thermco Nitride Down Waiting Burn Box Up ZYGO up GAAS 22 UP GAAS 23 UP SiH4 for furnaces Auto changeover working well A on line 630 PSI -------------- next part -------------- An HTML attachment was scrubbed... URL: From tberg at snf.stanford.edu Thu Dec 2 06:30:24 2004 From: tberg at snf.stanford.edu (Ted Berg) Date: Thu, 02 Dec 2004 06:30:24 -0800 Subject: [Fwd: Diffusion Morning Report 12/02/04] Message-ID: <41AF2700.8010309@snf.stanford.edu> -------- Original Message -------- Subject: Diffusion Morning Report 12/02/04 Date: Thu, 02 Dec 2004 06:26:26 -0800 From: Ted Berg To: interested furnace people Good Morning All, Looking OK this morning. Tylan Nitride and Poly are back up after pulls and under observation. Thermco poly is down for a cracked tube will go out for repair. Epi's gas panel is being rebuilt. Everything else looks OK for now. . Date: 12/2/2004 Tube Name/Number Status Comments THICKNESS-Change at Tylan 1 Up Tylan 2 Up Tylan 3 Up Tylan 4 Up Tylan 5-BBr3 Up Tylan 6-POCl3 Up Tylan 7-TEOS2 down Qual testing Tylan 8-SiGe Up 12.88/30 Tylan 9-Poly Up .66/30 Tylan 10-Nitride Up 0/30 Tylan 11-BPSG-LTO Up 17.56/30 Tylan 12-FGA Up Tystar Up 19.98/30 Doped Poly GONE TEOS up Tylan 16 N/A Thermco 1 Up Thermco 2 Up Thermco Poly down Cracked tube Thermco Nitride Down Waiting Burn Box Up ZYGO up GAAS 22 UP GAAS 23 UP SiH4 for furnaces Auto changeover working well A on line 630 PSI -------------- next part -------------- An HTML attachment was scrubbed... URL: From tberg at snf.stanford.edu Fri Dec 3 06:37:05 2004 From: tberg at snf.stanford.edu (Ted Berg) Date: Fri, 03 Dec 2004 06:37:05 -0800 Subject: Diffusion Morning Report 12/03/04 Message-ID: <41B07A11.9040402@snf.stanford.edu> Good Morning All, Looking Ok this morning after a very busy week, Thank to Mike who did 3 tube pulls this week and Ray who fought with the Epi gas panel. Tylan Nitride under observation. Hopefully Epi will be back up today. Ebeam vacum is OK again. Problems reported on LTO-phosphine flow -checking it out. Thermco Poly tube out for repair. Everything else looks ok for now. . Date: 12/3/2004 Tube Name/Number Status Comments THICKNESS-Change at Tylan 1 Up Tylan 2 Up Tylan 3 Up Tylan 4 Up Tylan 5-BBr3 Up Tylan 6-POCl3 Up Tylan 7-TEOS2 down Qual testing Tylan 8-SiGe Up 12.88/30 Tylan 9-Poly Up .74/30 Tylan 10-Nitride Up .25/30 Tylan 11-BPSG-LTO Up 17.61/30 Tylan 12-FGA Up Tystar Up 19.98/30 Doped Poly GONE TEOS up Tylan 16 N/A Thermco 1 Up Thermco 2 Up Thermco Poly down Cracked tube Thermco Nitride Down Waiting Burn Box Up ZYGO up GAAS 22 UP GAAS 23 UP SiH4 for furnaces Auto changeover working well A on line 630 PSI -------------- next part -------------- An HTML attachment was scrubbed... URL: From nanotech at nsti.org Sun Dec 5 23:34:54 2004 From: nanotech at nsti.org (BioNano 2005) Date: Sun, 5 Dec 2004 23:34:54 -0800 Subject: BioNano 2005 Abstract Deadline Message-ID: An HTML attachment was scrubbed... URL: From tberg at snf.stanford.edu Mon Dec 6 06:48:28 2004 From: tberg at snf.stanford.edu (Ted Berg) Date: Mon, 06 Dec 2004 06:48:28 -0800 Subject: Diffusion Morning Report 12/06/04 Message-ID: <41B4713C.8050508@snf.stanford.edu> Good Morning all, Looking Good this morning. Had aproblem with the burn box yesterday and pressure was high again this morning. Tylan Nitride under observation . Thermco poly tube out for repair. Teos 2 testing. Ray worked on the HCL for epi this weekend and it seems to be holding. Everything else seems to be OK for now. . Date: 12/6/2004 Tube Name/Number Status Comments THICKNESS-Change at Tylan 1 Up Tylan 2 Up Tylan 3 Up Tylan 4 Up Tylan 5-BBr3 Up Tylan 6-POCl3 Up Tylan 7-TEOS2 down Qual testing Tylan 8-SiGe Up 12.88/30 Tylan 9-Poly Up 7.4/30 Tylan 10-Nitride Up .25/30 Tylan 11-BPSG-LTO Up 19.891/30 Tylan 12-FGA Up Tystar Up 19.98/30 Doped Poly GONE TEOS up Tylan 16 N/A Thermco 1 Up Thermco 2 Up Thermco Poly down Cracked tube Thermco Nitride Down Waiting Burn Box Up ZYGO up GAAS 22 UP GAAS 23 UP SiH4 for furnaces Auto changeover working well A on line 630 PSI -------------- next part -------------- An HTML attachment was scrubbed... URL: From tberg at snf.stanford.edu Tue Dec 7 06:32:06 2004 From: tberg at snf.stanford.edu (Ted Berg) Date: Tue, 07 Dec 2004 06:32:06 -0800 Subject: Diffusion Morning Report 12/07/04 Message-ID: <41B5BEE6.9050309@snf.stanford.edu> Good Morning All, Looking good this morning. Nitride is still under observation. Burn box was cleaned yesterday. THermco poly tube should be back today. TEOS 2 testing. Everything else looks OK for now. . Date: 12/7/2004 Tube Name/Number Status Comments THICKNESS-Change at Tylan 1 Up Tylan 2 Up Tylan 3 Up Tylan 4 Up Tylan 5-BBr3 Up Tylan 6-POCl3 Up Tylan 7-TEOS2 down Qual testing Tylan 8-SiGe Up 1.0/30 Tylan 9-Poly Up 9.3/30 Tylan 10-Nitride yellow observation 1.25/30 Tylan 11-BPSG-LTO Up 20.4/30 Tylan 12-FGA Up Tystar Up 19.98/30 Doped Poly GONE TEOS up Tylan 16 N/A Thermco 1 Up Thermco 2 Up Thermco Poly down Cracked tube Thermco Nitride Down Waiting Burn Box Up ZYGO up GAAS 22 UP GAAS 23 UP SiH4 for furnaces Auto changeover working well A on line 630 PSI -------------- next part -------------- An HTML attachment was scrubbed... URL: From tberg at snf.stanford.edu Wed Dec 8 06:58:11 2004 From: tberg at snf.stanford.edu (Ted Berg) Date: Wed, 08 Dec 2004 06:58:11 -0800 Subject: Diffusion Morning Report 12/08/04 Message-ID: <41B71683.4090304@snf.stanford.edu> Good Morning All, Looking good this morning. Burn box had a drain issue this morning but it seems ok now. THermco poly is back up and coated. TEOS2 still testing Tylan Nitride is still under observation. Epi Germane pressure is holding so we will turn it back on later this morning. Everything else looks OK for now. . Date: 12/8/2004 Tube Name/Number Status Comments THICKNESS-Change at Tylan 1 Up Tylan 2 Up Tylan 3 Up Tylan 4 Up Tylan 5-BBr3 Up Tylan 6-POCl3 Up Tylan 7-TEOS2 down Qual testing Tylan 8-SiGe Up 12.33.0/30 Tylan 9-Poly Up 9.3/30 Tylan 10-Nitride yellow observation 1.5/30 Tylan 11-BPSG-LTO Up 22.4/30 Tylan 12-FGA Up Tystar Up 19.98/30 Doped Poly GONE TEOS up Tylan 16 N/A Thermco 1 Up Thermco 2 Up Thermco Poly yellow Cracked tube replaced and coated Thermco Nitride Down Waiting Burn Box Up ZYGO up GAAS 22 UP GAAS 23 UP SiH4 for furnaces Auto changeover working well A on line 630 PSI -------------- next part -------------- An HTML attachment was scrubbed... URL: From tberg at snf.stanford.edu Thu Dec 9 06:40:35 2004 From: tberg at snf.stanford.edu (Ted Berg) Date: Thu, 09 Dec 2004 06:40:35 -0800 Subject: Diffusion Morning Report 12/09/04 Message-ID: <41B863E3.6020304@snf.stanford.edu> Good Morning All, Looking good this morning. Tylan Nitride is still under observation for particles. TEOS2 and Thermco Poly are testing. Everything else looks OK for now. . Date: 12/9/2004 Tube Name/Number Status Comments THICKNESS-Change at Tylan 1 Up Tylan 2 Up Tylan 3 Up Tylan 4 Up Tylan 5-BBr3 Up Tylan 6-POCl3 Up Tylan 7-TEOS2 down Qual testing Tylan 8-SiGe Up 12.33.0/30 Tylan 9-Poly Up 9.4/30 Tylan 10-Nitride yellow observation 1.8/30 Tylan 11-BPSG-LTO Up 23.4/30 Tylan 12-FGA Up Tystar Up 23.3/30 Doped Poly GONE TEOS up Tylan 16 N/A Thermco 1 Up Thermco 2 Up Thermco Poly yellow Thermco Nitride Down Waiting Burn Box Up ZYGO up GAAS 22 UP GAAS 23 UP SiH4 for furnaces Auto changeover working well A on line 630 PSI -------------- next part -------------- An HTML attachment was scrubbed... URL: From nanotech at nsti.org Thu Dec 9 16:08:22 2004 From: nanotech at nsti.org (Nano Science and Technology Institute) Date: Thu, 9 Dec 2004 16:08:22 -0800 Subject: Nanotech Courses - Davos Switzerland - Spring 2005 Message-ID: An HTML attachment was scrubbed... URL: From tberg at snf.stanford.edu Fri Dec 10 06:57:18 2004 From: tberg at snf.stanford.edu (Ted Berg) Date: Fri, 10 Dec 2004 06:57:18 -0800 Subject: Diffusion Morning Report 12/10/04 Message-ID: <41B9B94E.1000300@snf.stanford.edu> Good morning All, Looking Good this morning. Burn box clean this morning. Tylan Nitride is still under observation for particles. Thermco poly and TEOS2 still testing. Everything else looking OK for now. . Date: 12/10/2004 Tube Name/Number Status Comments THICKNESS-Change at Tylan 1 Up Tylan 2 Up Tylan 3 Up Tylan 4 Up Tylan 5-BBr3 Up Tylan 6-POCl3 Up Tylan 7-TEOS2 down Qual testing Tylan 8-SiGe Up 12.33.0/30 Tylan 9-Poly Up 9.47/30 Tylan 10-Nitride yellow observation 1.91/30 Tylan 11-BPSG-LTO Up 23.4/30 Tylan 12-FGA Up Tystar Up 23.3/30 Doped Poly GONE TEOS up Tylan 16 N/A Thermco 1 Up Thermco 2 Up Thermco Poly yellow Thermco Nitride Down Waiting Burn Box Up Cleaned this morning ZYGO up GAAS 22 UP GAAS 23 UP SiH4 for furnaces Auto changeover working well A on line 630 PSI -------------- next part -------------- An HTML attachment was scrubbed... URL: From tberg at snf.stanford.edu Mon Dec 13 08:22:11 2004 From: tberg at snf.stanford.edu (Ted Berg) Date: Mon, 13 Dec 2004 08:22:11 -0800 Subject: Diffusion Morning Report 12/13/04 Message-ID: <41BDC1B3.3010104@snf.stanford.edu> Good Morning All, Looking good after pump change in LTO Nitride is still under observation. Thermco Poly and TEOS2 testing Everything else looks OK for now. . Date: 12/13/2004 Tube Name/Number Status Comments THICKNESS-Change at Tylan 1 Up Tylan 2 Up Tylan 3 Up Tylan 4 Up Tylan 5-BBr3 Up Tylan 6-POCl3 Up Tylan 7-TEOS2 down Qual testing Tylan 8-SiGe Up 12.33.0/30 Tylan 9-Poly Up 9.76/30 Tylan 10-Nitride yellow observation 1.91/30 Tylan 11-BPSG-LTO Up Replaced pump This morning 24.9/30 Tylan 12-FGA Up Tystar Up 23.3/30 Doped Poly GONE TEOS up Tylan 16 N/A Thermco 1 Up Thermco 2 Up Thermco Poly yellow Thermco Nitride Down Waiting Burn Box Up Cleaned this morning ZYGO up GAAS 22 UP GAAS 23 UP SiH4 for furnaces Auto changeover working well A on line 630 PSI -------------- next part -------------- An HTML attachment was scrubbed... URL: From tberg at snf.stanford.edu Tue Dec 14 06:26:43 2004 From: tberg at snf.stanford.edu (Ted Berg) Date: Tue, 14 Dec 2004 06:26:43 -0800 Subject: Diffusion Morning Report 12/14/04 Message-ID: <41BEF823.1080003@snf.stanford.edu> Good Morning All, Looking prttty good this morning. LTO is moving quickly toward pull and clean. Tylan Nitride stiill under observation. Thermco poly and TEOS2 testing. Epi has loader issues. Everything else looks OK for now. . Date: 12/14/2004 Tube Name/Number Status Comments THICKNESS-Change at Tylan 1 Up Tylan 2 Up Tylan 3 Up Tylan 4 Up Tylan 5-BBr3 Up Tylan 6-POCl3 Up Tylan 7-TEOS2 down Qual testing Tylan 8-SiGe Up 12.33.0/30 Tylan 9-Poly Up 9.76/30 Tylan 10-Nitride yellow observation 1.91/30 Tylan 11-BPSG-LTO Up 26.52/30 Tylan 12-FGA Up Tystar Up 23.3/30 Doped Poly GONE TEOS up Tylan 16 N/A Thermco 1 Up Thermco 2 Up Thermco Poly yellow Thermco Nitride Down Waiting Burn Box Up ZYGO up GAAS 22 UP GAAS 23 UP SiH4 for furnaces Auto changeover working well A on line 630 PSI -------------- next part -------------- An HTML attachment was scrubbed... URL: From seymour at snf.stanford.edu Wed Dec 15 07:44:04 2004 From: seymour at snf.stanford.edu (Ray Seymour) Date: Wed, 15 Dec 2004 07:44:04 -0800 Subject: Diffusion Morning Report Message-ID: <41C05BC4.2A39C2E@snf.stanford.edu> Morning, Ted is out this morning. Everything looking pretty good. Nitride is under observation . All else is looking good. Diffusion Date: 12/15/2004 Tube Name/Number Status Comments THICKNESS-Change at Tylan 1 Up Tylan 2 Up Tylan 3 Up Tylan 4 Up Tylan 5-BBr3 Up Tylan 6-POCl3 Up Tylan 7-TEOS2 Down Qual testing Tylan 8-SiGe Up 12.33/30 Tylan 9-Poly Up 9.76/30 Tylan 10-Nitride Up observation 1.91/30 Tylan 11-BPSG-LTO Up 26.52/30 Tylan 12-FGA Up Tystar Up 23.3/30 Doped Poly GONE TEOS Up Tylan 16 N/A Yhermco 1 UP Thermco 1 UP Thermco Poly Yellow Thermco Nitride Down Waiting Burn Box Up ZYGO Up GAAS 22 UP GAAS 23 UP SiH4 for furnaces Auto changeover working well A on line 630 PSI -------------- next part -------------- An HTML attachment was scrubbed... URL: From nanotech at nsti.org Wed Dec 15 22:50:00 2004 From: nanotech at nsti.org (NSTI Nanotech Ventures) Date: Wed, 15 Dec 2004 22:50:00 -0800 Subject: Nanotech Ventures 2005 - Tokyo & California Message-ID: An HTML attachment was scrubbed... URL: From tberg at snf.stanford.edu Thu Dec 16 06:33:50 2004 From: tberg at snf.stanford.edu (Ted Berg) Date: Thu, 16 Dec 2004 06:33:50 -0800 Subject: Diffusion Morning Report 12/16/04 Message-ID: <41C19CCE.20207@snf.stanford.edu> Good Morning all, Getting ready for the Holiday shutdown tomorrow morning. LTO is at 29.? and will be changed during the shutdown. Nitride still under observation. Thermco poly is testing doped. TEOS 2 is testing. Everything else looks OK for now. . Date: 12/16/2004 Tube Name/Number Status Comments THICKNESS-Change at Tylan 1 Up Tylan 2 Up Tylan 3 Up Tylan 4 Up Tylan 5-BBr3 Up Tylan 6-POCl3 Up Tylan 7-TEOS2 down Qual testing Tylan 8-SiGe Up 12.33.0/30 Tylan 9-Poly Up 9.76/30 Tylan 10-Nitride yellow observation 2.28/30 Tylan 11-BPSG-LTO Up 29.16/30 Tylan 12-FGA Up Tystar Up 23.3/30 Doped Poly GONE TEOS up Tylan 16 N/A Thermco 1 Up Thermco 2 Up Thermco Poly yellow testing doped Thermco Nitride Down Waiting Burn Box Up ZYGO up GAAS 22 UP GAAS 23 UP SiH4 for furnaces Auto changeover working well A on line 620 PSI -------------- next part -------------- An HTML attachment was scrubbed... URL: