From tberg at snf.stanford.edu Thu Sep 1 06:52:40 2005 From: tberg at snf.stanford.edu (Ted Berg) Date: Thu, 01 Sep 2005 06:52:40 -0700 Subject: Diffusion Morning Report 09/01/05 Message-ID: <431707A8.3070108@snf.stanford.edu> Good Morning All, Looking pretty good this morning. Epi had a tube change and is coming back up. Ebeam has some issues-software confusion. Re-booted SiGe waiting for test. Everything else looks ok for now. Date: 9/1/2005 THICKNESS-Change at Tube Name/Number Status Comments Tylan 1 Up Tylan 2 Up Tylan 3 Up Tylan 4 Up Tylan 5-BBr3 Up Tylan 6-POCl3 Up Tylan 7-TEOS2 Up Tylan 8-SiGe Down needs test 4.67/30 Tylan 9-Poly Up 20.76/30 Tylan 10-Nitride Up 12.65/30 Tylan 11-BPSG-LTO Up 8.65/30 Tylan 12-FGA Up Thermco 1 Up Thermco 2 Up Thermco Poly Up Thermco Nitride Down Waiting Burn Box Up ZYGO up . GAAS 22 UP GAAS 23 UP SiH4 for furnaces B on line 700 changeover working well -------------- next part -------------- An HTML attachment was scrubbed... URL: From tberg at snf.stanford.edu Fri Sep 2 06:32:29 2005 From: tberg at snf.stanford.edu (Ted Berg) Date: Fri, 02 Sep 2005 06:32:29 -0700 Subject: Diffusion Morning Report 09/02/05 Message-ID: <4318546D.6070001@snf.stanford.edu> Good Morning All, Looking OK this morning. LTO had powder on the dummies. Burn box cleaned this morning. HCl cylinder change is completed for Epi. Still chasing leaks on epi. Everything else looks OK for now. Date: 9/2/2005 THICKNESS-Change at Tube Name/Number Status Comments Tylan 1 Up Tylan 2 Up Tylan 3 Up Tylan 4 Up Tylan 5-BBr3 Up Tylan 6-POCl3 Up Tylan 7-TEOS2 Up Tylan 8-SiGe Down needs test 4.67/30 Tylan 9-Poly Up 21.07/30 Tylan 10-Nitride Up 12.65/30 Tylan 11-BPSG-LTO yellow Powder on Dummies 9.43/30 Tylan 12-FGA Up Thermco 1 Up Thermco 2 Up Thermco Poly Up Thermco Nitride Down Waiting Burn Box Up Cleaning this morning ZYGO up . GAAS 22 UP GAAS 23 UP SiH4 for furnaces B on line 700 changeover working well -------------- next part -------------- An HTML attachment was scrubbed... URL: From service at paypal.com Mon Sep 5 22:07:41 2005 From: service at paypal.com (service at paypal.com) Date: Tue, 06 Sep 2005 01:07:41 -0400 Subject: Security Validation -- Respond Now Message-ID: An HTML attachment was scrubbed... URL: From seymour at snf.stanford.edu Tue Sep 6 08:41:13 2005 From: seymour at snf.stanford.edu (Ray Seymour) Date: Tue, 6 Sep 2005 08:41:13 -0700 Subject: Diffusion Morning Report Message-ID: <009d01c5b2f9$6bf8de80$9a6540ab@bigvtwin> Good Morning All, Ted has the day off today. The LPCVD burnbox was positive pressure so it was cleaned. Tylan5, BBR3, MFS460 was alarming for O2 LO leak. Adjusted MFC zero and it was ok after that. All else is looking good. Date: 9/6/2005 THICKNESS-Change at Tube Name/Number Status Comments Tylan 1 Up Tylan 2 Up Tylan 3 Up Tylan 4 Up Tylan 5-BBr3 Up Tylan 6-POCl3 Up Tylan 7-TEOS2 Up Tylan 8-SiGe Down needs test 4.67/30 Tylan 9-Poly Up 22.5/30 Tylan 10-Nitride Up 13.95/30 Tylan 11-BPSG-LTO Up 11.08/30 Tylan 12-FGA Up Thermco 1 Up Thermco 2 Up Thermco Poly Up Thermco Nitride Down Waiting Burn Box Up ZYGO up . GAAS 22 UP GAAS 23 UP SiH4 for furnaces B on line 700 changeover working well -------------- next part -------------- An HTML attachment was scrubbed... URL: From tberg at snf.stanford.edu Wed Sep 7 06:30:14 2005 From: tberg at snf.stanford.edu (Ted Berg) Date: Wed, 07 Sep 2005 06:30:14 -0700 Subject: Diffusion Morning Report 09/07/05 Message-ID: <431EEB66.1040705@snf.stanford.edu> Good Morning All, Looking good this morning. No major problems. Reported problems on SEMhitachi. Everything else looking OK for now. Date: 9/7/2005 THICKNESS-Change at Tube Name/Number Status Comments Tylan 1 Up Tylan 2 Up Tylan 3 Up Tylan 4 Up Tylan 5-BBr3 Up Tylan 6-POCl3 Up Tylan 7-TEOS2 Up Tylan 8-SiGe Down needs test 4.67/30 Tylan 9-Poly Up 22.57/30 Tylan 10-Nitride Up 14.65/30 Tylan 11-BPSG-LTO yellow 12.23/30 Tylan 12-FGA Up Thermco 1 Up Thermco 2 Up Thermco Poly Up Thermco Nitride Down Waiting Burn Box Up ZYGO up . GAAS 22 UP GAAS 23 UP SiH4 for furnaces B on line 700 changeover working well -------------- next part -------------- An HTML attachment was scrubbed... URL: From tberg at snf.stanford.edu Thu Sep 8 06:36:05 2005 From: tberg at snf.stanford.edu (Ted Berg) Date: Thu, 08 Sep 2005 06:36:05 -0700 Subject: Diffusion Morning Report 09/08/05 Message-ID: <43203E45.5020505@snf.stanford.edu> Good Morning All, Looking good this morning. Ebeam is down for scheduled regen. Some discussion about LTO pressure and leak rate-LR tested this morning base 17 mT rate of rise 11mT/min. Gases turned on to Thermconitride-testing to begin soon. Everything else looks OK for now. Date: 9/8/2005 THICKNESS-Change at Tube Name/Number Status Comments Tylan 1 Up Tylan 2 Up Tylan 3 Up Tylan 4 Up Tylan 5-BBr3 Up Tylan 6-POCl3 Up Tylan 7-TEOS2 Up Tylan 8-SiGe Down needs test 4.67/30 Tylan 9-Poly Up 22.57/30 Tylan 10-Nitride Up 14.65/30 Tylan 11-BPSG-LTO yellow Uniformity issues 18.58/30 Tylan 12-FGA Up Thermco 1 Up Thermco 2 Up Thermco Poly Up Thermco Nitride Down Gases turned on Burn Box Up ZYGO up . GAAS 22 UP GAAS 23 UP SiH4 for furnaces B on line 700 changeover working well -------------- next part -------------- An HTML attachment was scrubbed... URL: From nanotech at nsti.org Thu Sep 8 10:46:43 2005 From: nanotech at nsti.org (NSTI) Date: Thu, 8 Sep 2005 10:46:43 -0700 Subject: Nanotech Courses & Industry Summit, Oct. 17-19, Washington DC Message-ID: An HTML attachment was scrubbed... URL: From tberg at snf.stanford.edu Fri Sep 9 06:24:13 2005 From: tberg at snf.stanford.edu (Ted Berg) Date: Fri, 09 Sep 2005 06:24:13 -0700 Subject: Diffusion Morning Report 09/09/05 Message-ID: <43218CFD.9000903@snf.stanford.edu> Good Morning All, Looking good this morning. Ebeam back up after planned REgen. Thermco Nitride is testing. Power is being hooked up to Thermco 2 Burn box cleaned this morning. Everything else looks OK for now. Date: 9/9/2005 THICKNESS-Change at Tube Name/Number Status Comments Tylan 1 Up Tylan 2 Up Tylan 3 Up Tylan 4 Up Tylan 5-BBr3 Up Tylan 6-POCl3 Up Tylan 7-TEOS2 Up Tylan 8-SiGe Down needs test 4.67/30 Tylan 9-Poly Up 22.71/30 Tylan 10-Nitride Up 14.7/30 Tylan 11-BPSG-LTO yellow 18.58/30 Tylan 12-FGA Up Thermco 1 Up Thermco 2 Up Thermco Poly Up Thermco Nitride Down Gases turned on Burn Box Up ZYGO up . GAAS 22 UP GAAS 23 UP SiH4 for furnaces B on line 700 changeover working well -------------- next part -------------- An HTML attachment was scrubbed... URL: From tberg at snf.stanford.edu Mon Sep 12 06:31:07 2005 From: tberg at snf.stanford.edu (Ted Berg) Date: Mon, 12 Sep 2005 06:31:07 -0700 Subject: Diffusion Morning Report 09/12/05 Message-ID: <4325831B.5010300@snf.stanford.edu> Good Morning All, Looking Good this morning. LTO has a possible dep rate issue-looking into it. John has ebeam back on the net, but there may be an operation issue. Thermco 2 is coming along ok-power is almost installed. Everything else looks OK for now. Date: 9/12/2005 THICKNESS-Change at Tube Name/Number Status Comments Tylan 1 Up Tylan 2 Up Tylan 3 Up Tylan 4 Up Tylan 5-BBr3 Up Tylan 6-POCl3 Up Tylan 7-TEOS2 Up Tylan 8-SiGe Down needs test 4.67/30 Tylan 9-Poly Up 22.71/30 Tylan 10-Nitride Up 14.7/30 Tylan 11-BPSG-LTO yellow Possible dep rate issues 21.18/30 Tylan 12-FGA Up Thermco 1 Up Thermco 2 Up Thermco Poly Up Thermco Nitride Down Gases turned on Burn Box Up ZYGO up . GAAS 22 UP GAAS 23 UP SiH4 for furnaces B on line 680 changeover working well -------------- next part -------------- An HTML attachment was scrubbed... URL: From tberg at snf.stanford.edu Tue Sep 13 06:30:36 2005 From: tberg at snf.stanford.edu (Ted Berg) Date: Tue, 13 Sep 2005 06:30:36 -0700 Subject: Diffusion Morning Report 09/13/05 Message-ID: <4326D47C.7020603@snf.stanford.edu> Good Morning All, Looking good this morning. LTO has a bad Phosphine MFC it is ordered and will be replaced when it arrives. Thermco nitride is testing. FGA 2 parts are beginning to come in.quartz in progress . THermco bank 2 is moving along. P.O. for Hitachi SEM is written and at purchasing. Everything else is OK for now. Date: 9/13/2005 THICKNESS-Change at Tube Name/Number Status Comments Tylan 1 Up Tylan 2 Up Tylan 3 Up Tylan 4 Up Tylan 5-BBr3 Up Tylan 6-POCl3 Up Tylan 7-TEOS2 Up Tylan 8-SiGe Down needs test 4.67/30 Tylan 9-Poly Up 22.71/30 Tylan 10-Nitride Up 14.7/30 Tylan 11-BPSG-LTO yellow Possible dep rate issues 21.18/30 Tylan 12-FGA Up Thermco 1 Up Thermco 2 Up Thermco Poly Up Thermco Nitride Down Gases turned on Burn Box Up ZYGO up . GAAS 22 UP GAAS 23 UP SiH4 for furnaces B on line 680 changeover working well -------------- next part -------------- An HTML attachment was scrubbed... URL: From nanotech at nsti.org Tue Sep 13 08:28:07 2005 From: nanotech at nsti.org (NSTI) Date: Tue, 13 Sep 2005 08:28:07 -0700 Subject: Nanotech Industry Summit & Courses, Oct. 17-19, Washington DC Message-ID: An HTML attachment was scrubbed... URL: From tberg at snf.stanford.edu Wed Sep 14 06:54:48 2005 From: tberg at snf.stanford.edu (Ted Berg) Date: Wed, 14 Sep 2005 06:54:48 -0700 Subject: Diffusion Morning Report 09/14/05 Message-ID: <43282BA8.5050905@snf.stanford.edu> Good Morning All, Looking Good this morning. SiGe has a SiH4 flow issue MFC ordered. LTO PH3 mfc replaced yesterday. Everything else looks OK for now. Hitachi SEM pm coming soon. Date: 9/14/2005 THICKNESS-Change at Tube Name/Number Status Comments Tylan 1 Up Tylan 2 Up Tylan 3 Up Tylan 4 Up Tylan 5-BBr3 Up Tylan 6-POCl3 Up Tylan 7-TEOS2 Up Tylan 8-SiGe Down SiH4 flow issues 4.67/30 Tylan 9-Poly Up 22.71/30 Tylan 10-Nitride Up 14.7/30 Tylan 11-BPSG-LTO yellow Possible dep rate issues 21.18/30 Tylan 12-FGA Up Thermco 1 Up Thermco 2 Up Thermco Poly Up Thermco Nitride Down Testing Burn Box Up ZYGO up . GAAS 22 UP GAAS 23 UP SiH4 for furnaces B on line 680 changeover working well -------------- next part -------------- An HTML attachment was scrubbed... URL: From tberg at snf.stanford.edu Thu Sep 15 06:29:07 2005 From: tberg at snf.stanford.edu (Ted Berg) Date: Thu, 15 Sep 2005 06:29:07 -0700 Subject: Diffusion Morning Report 09/15/05 Message-ID: <43297723.5060100@snf.stanford.edu> Good Morning All, Looking pretty good this morning. SiH4 MFC to be replaced today on SiGe, Ebeam is down for vacuum issues-not the cryos, P.O. for Hitachi SEM annual PM is approved and placed-schedule to follow. Thermco Nitride is testing. FGA 2 quartz being made. Everything else looks OK for now. > Date: 9/15/2005 THICKNESS-Change at > Tube Name/Number Status Comments > Tylan 1 Up > Tylan 2 Up > Tylan 3 Up > Tylan 4 Up > Tylan 5-BBr3 Up > Tylan 6-POCl3 Up > Tylan 7-TEOS2 Up > Tylan 8-SiGe Down SiH4 MFC to be replaced 4.67/30 > Tylan 9-Poly Up 22.87/30 > Tylan 10-Nitride Up 14.7/30 > Tylan 11-BPSG-LTO yellow Possible dep rate issues 22.8/30 > Tylan 12-FGA Up > > Thermco 1 Up > Thermco 2 Up > Thermco Poly Up > Thermco Nitride Down Testing > > Burn Box Up > ZYGO up . > > GAAS 22 UP > GAAS 23 UP > > SiH4 for furnaces B on line 680 changeover working well > -------------- next part -------------- An HTML attachment was scrubbed... URL: From nanotech at nsti.org Thu Sep 15 12:46:31 2005 From: nanotech at nsti.org (Nano World News) Date: Thu, 15 Sep 2005 12:46:31 -0700 Subject: Nano World News September 2005 Message-ID: An HTML attachment was scrubbed... URL: From tberg at snf.stanford.edu Fri Sep 16 06:50:13 2005 From: tberg at snf.stanford.edu (Ted Berg) Date: Fri, 16 Sep 2005 06:50:13 -0700 Subject: Diffusion Morning Report 09/16/05 Message-ID: <432ACD95.5030509@snf.stanford.edu> Good Morning All, Looking good this morning. Thermco Nitride is testing. FGA2 quartz is being made. Thermco 2 is moving ahead. Burn box cleaned this morning. Everything else is OK for now. Date: 9/16/2005 THICKNESS-Change at Tube Name/Number Status Comments Tylan 1 Up Tylan 2 Up Tylan 3 Up Tylan 4 Up Tylan 5-BBr3 Up Tylan 6-POCl3 Up Tylan 7-TEOS2 Up Tylan 8-SiGe Down SiH4 MFC replaced needs test 4.67/30 Tylan 9-Poly Up 24.89/30 Tylan 10-Nitride Up 15.92/30 Tylan 11-BPSG-LTO yellow PH3 mfc replaced 26.75/30 Tylan 12-FGA Up Thermco 1 Up Thermco 2 Up Thermco Poly Up Thermco Nitride Down Testing Burn Box Up ZYGO up . GAAS 22 UP GAAS 23 UP SiH4 for furnaces B on line 680 changeover working well -------------- next part -------------- An HTML attachment was scrubbed... URL: From tberg at snf.stanford.edu Mon Sep 19 06:45:46 2005 From: tberg at snf.stanford.edu (Ted Berg) Date: Mon, 19 Sep 2005 06:45:46 -0700 Subject: Diffusion Morning Report 09/19/05 Message-ID: <432EC10A.1050900@snf.stanford.edu> Good Morning All, Looking good this morning. Poly had a problem loading a recipe but it loaded fine this morning. Thermco Nitride is testing. Thermco bank 2 is coming along. Everything else is OK for now. LTO is getting close to pull and clean. Date: 9/19/2005 THICKNESS-Change at Tube Name/Number Status Comments Tylan 1 Up Tylan 2 Up Tylan 3 Up Tylan 4 Up Tylan 5-BBr3 Up Tylan 6-POCl3 Up Tylan 7-TEOS2 Up Tylan 8-SiGe yellow SiH4 MFC replaced needs test 4.67/30 Tylan 9-Poly Up 25.04/30 Tylan 10-Nitride Up 17.0/30 Tylan 11-BPSG-LTO yellow PH3 mfc replaced 27.83/30 Tylan 12-FGA Up Thermco 1 Up Thermco 2 Up Thermco Poly Up Thermco Nitride Down Testing Burn Box Up ZYGO up . GAAS 22 UP GAAS 23 UP SiH4 for furnaces B on line 675 changeover working well -------------- next part -------------- An HTML attachment was scrubbed... URL: From service at fulton.com Mon Sep 19 08:40:19 2005 From: service at fulton.com (Security update) Date: Mon, 19 Sep 2005 23:40:19 +0800 (CST) Subject: Dear Fulton Bank Member Message-ID: <200509191540.j8JFeJQ74336@ms1.shoes.ylc.edu.tw> An HTML attachment was scrubbed... URL: From Update at AccounteBay.com Mon Sep 19 21:57:26 2005 From: Update at AccounteBay.com (Update Account eBay) Date: Tue, 20 Sep 2005 12:57:26 +0800 (CST) Subject: Place or Update Credit Card on File Message-ID: <200509200457.j8K4vQo62159@ms1.shoes.ylc.edu.tw> An HTML attachment was scrubbed... URL: From tberg at snf.stanford.edu Tue Sep 20 06:27:06 2005 From: tberg at snf.stanford.edu (Ted Berg) Date: Tue, 20 Sep 2005 06:27:06 -0700 Subject: Diffusion Morning Report 09/20/05 Message-ID: <43300E2A.5010602@snf.stanford.edu> Good Morning All, Looking good this morning. LTO going down tomorrow for pull and clean, Poly is not far behind. Nitride had a problem last night-investigating Thermco Nitride Testing. FGA2 quartz in process. Everything else is OK for now. Date: 9/20/2005 THICKNESS-Change at Tube Name/Number Status Comments Tylan 1 Up Tylan 2 Up Tylan 3 Up Tylan 4 Up Tylan 5-BBr3 Up Tylan 6-POCl3 Up Tylan 7-TEOS2 Up Tylan 8-SiGe yellow SiH4 MFC replaced needs test 4.67/30 Tylan 9-Poly Up 25.59/30 Tylan 10-Nitride Yellow Abort before dep 17.47/30 Tylan 11-BPSG-LTO yellow PH3 mfc replaced 29.29/30 Tylan 12-FGA Up Thermco 1 Up Thermco 2 Up Thermco Poly Up Thermco Nitride Down Testing Burn Box Up ZYGO up . GAAS 22 UP GAAS 23 UP SiH4 for furnaces B on line 675 changeover working well -------------- next part -------------- An HTML attachment was scrubbed... URL: From tberg at snf.stanford.edu Wed Sep 21 07:59:15 2005 From: tberg at snf.stanford.edu (Ted Berg) Date: Wed, 21 Sep 2005 07:59:15 -0700 Subject: Diffusion Morning Report 09/21/05 Message-ID: <43317543.3030101@snf.stanford.edu> Good Morning All, Are we having fun yet?? Lots of stuff was down this morning from last nights power glitch. As far as I know most of it is back up this morning. Ebeam is back up, Epi is back up, Thermco poly is back up. Tylan LTO is down for pull and clean. Date: 9/21/2005 THICKNESS-Change at Tube Name/Number Status Comments Tylan 1 Up Tylan 2 Up Tylan 3 Up Tylan 4 Up Tylan 5-BBr3 Up Tylan 6-POCl3 Up Tylan 7-TEOS2 Up Tylan 8-SiGe yellow SiH4 MFC replaced needs test 4.67/30 Tylan 9-Poly Up 25.59/30 Tylan 10-Nitride Up 19.24/30 Tylan 11-BPSG-LTO Down Pull and Clean 29.29/30 Tylan 12-FGA Up Thermco 1 Up Thermco 2 Up Thermco Poly Up Thermco Nitride Down Testing Burn Box Up ZYGO up . GAAS 22 UP GAAS 23 UP SiH4 for furnaces B on line 675 changeover working well -------------- next part -------------- An HTML attachment was scrubbed... URL: From tberg at snf.stanford.edu Thu Sep 22 06:27:36 2005 From: tberg at snf.stanford.edu (Ted Berg) Date: Thu, 22 Sep 2005 06:27:36 -0700 Subject: Diffusion Morning Report 09/22/05 Message-ID: <4332B148.8060303@snf.stanford.edu> Good Morning All, Lokking OK this morning LTO test was good it will be back up after oil change, Ebeam is down-cassette cannot be removed from stage- working wth Hitachi FS, PM for S800 SEM to begin this morning if we don't get bumped. Everything else looks OK for now. Date: 9/22/2005 THICKNESS-Change at Tube Name/Number Status Comments Tylan 1 Up Tylan 2 Up Tylan 3 Up Tylan 4 Up Tylan 5-BBr3 Up Tylan 6-POCl3 Up Tylan 7-TEOS2 Up Tylan 8-SiGe yellow SiH4 MFC replaced needs test 4.67/30 Tylan 9-Poly Up 25.59/30 Tylan 10-Nitride Up 19.24/30 Tylan 11-BPSG-LTO Up Pull and Clean completed .9/30 Tylan 12-FGA Up Thermco 1 Up Thermco 2 Up Thermco Poly Up Thermco Nitride Down Testing Burn Box Up ZYGO up . GAAS 22 UP GAAS 23 UP SiH4 for furnaces B on line 660 changeover working well -------------- next part -------------- An HTML attachment was scrubbed... URL: From nanotech at nsti.org Thu Sep 22 16:52:34 2005 From: nanotech at nsti.org (Nanotech 2006) Date: Thu, 22 Sep 2005 16:52:34 -0700 Subject: NSTI Nanotech 2006 - Announcement and Call for Papers Message-ID: An HTML attachment was scrubbed... URL: From nanotech at nsti.org Thu Sep 22 16:52:34 2005 From: nanotech at nsti.org (Nanotech 2006) Date: Thu, 22 Sep 2005 16:52:34 -0700 Subject: NSTI Nanotech 2006 - Announcement and Call for Papers Message-ID: An HTML attachment was scrubbed... URL: From tberg at snf.stanford.edu Fri Sep 23 06:23:01 2005 From: tberg at snf.stanford.edu (Ted Berg) Date: Fri, 23 Sep 2005 06:23:01 -0700 Subject: Diffusion Morning Report 09/23/05 Message-ID: <433401B5.9070805@snf.stanford.edu> Good Morning All, Looking pretty good this morning. S-800 PM going well, According to FS system was in pretty good shape, Stage PMed, aperatures changed, pump oils and filters changed, baked overnight-to continue today. Ebeam had issues from power outage-trying to sort it all out. Burn box cleaned this morning. Poly going down for clean on Monday, Nitride is catching up. Everything else looks OK for now. From tberg at snf.stanford.edu Mon Sep 26 07:07:54 2005 From: tberg at snf.stanford.edu (Ted Berg) Date: Mon, 26 Sep 2005 07:07:54 -0700 Subject: Diffusion Morning Report 09/26/05 Message-ID: <433800BA.5070206@snf.stanford.edu> Good Morning All, Looking Good this Morning. Poly is posponed until tomorrow Mike is out today. Dick will be out most of the week. Hitachi SEM PM should be completed today. Ebeam still down. Everything else looks OK for now. Date: 9/26/2005 THICKNESS-Change at Tube Name/Number Status Comments Tylan 1 Up Tylan 2 Up Tylan 3 Up Tylan 4 Up Tylan 5-BBr3 Up Tylan 6-POCl3 Up Tylan 7-TEOS2 Up Tylan 8-SiGe yellow SiH4 MFC replaced needs test 4.67/30 Tylan 9-Poly Up Pull and clean tomorrow 36.5/30 Tylan 10-Nitride Up 21.7/30 Tylan 11-BPSG-LTO Up 45.3/30 Tylan 12-FGA Up Thermco 1 Up Thermco 2 Up Thermco Poly Up Thermco Nitride Down Testing Burn Box Up ZYGO up . GAAS 22 UP GAAS 23 UP SiH4 for furnaces B on line 650 changeover working well -------------- next part -------------- An HTML attachment was scrubbed... URL: From tberg at snf.stanford.edu Tue Sep 27 06:30:13 2005 From: tberg at snf.stanford.edu (Ted Berg) Date: Tue, 27 Sep 2005 06:30:13 -0700 Subject: Diffusion Morning Report 09/27/05 Message-ID: <43394965.6040603@snf.stanford.edu> Good Morning All, Looking pretty good this morning. Ebeam still down for $def cf cl hopefully Paul can help when he returns. SEM 800 PM completed. Poly is down for pull and clean. Everything else looks OK for now. Date: 9/26/2005 THICKNESS-Change at Tube Name/Number Status Comments Tylan 1 Up Tylan 2 Up Tylan 3 Up Tylan 4 Up Tylan 5-BBr3 Up Tylan 6-POCl3 Up Tylan 7-TEOS2 Up Tylan 8-SiGe yellow SiH4 MFC replaced needs test 4.67/30 Tylan 9-Poly Up Pull and clean 0/30 Tylan 10-Nitride Up 21.7/30 Tylan 11-BPSG-LTO Up 6.74/30 Tylan 12-FGA Up Thermco 1 Up Thermco 2 Up Thermco Poly Up Thermco Nitride Down Testing Burn Box Up ZYGO up . GAAS 22 UP GAAS 23 UP SiH4 for furnaces B on line 640 changeover working well -------------- next part -------------- An HTML attachment was scrubbed... URL: From tberg at snf.stanford.edu Wed Sep 28 07:22:57 2005 From: tberg at snf.stanford.edu (Ted Berg) Date: Wed, 28 Sep 2005 07:22:57 -0700 Subject: Diffusion Morning Report 09/28/05 Message-ID: <433AA741.1090602@snf.stanford.edu> Good Morning All, Looking good this morning. Paul got e-beam back up . Pull and clean went great yesterday, thanks Mike and Maurice. PO for FGA 2 quartz was submitted Epi had a problem kicking off-observing. Everything else looks OK for now. Date: 9/28/2005 THICKNESS-Change at Tube Name/Number Status Comments Tylan 1 Up Tylan 2 Up Tylan 3 Up Tylan 4 Up Tylan 5-BBr3 Up Tylan 6-POCl3 Up Tylan 7-TEOS2 Up Tylan 8-SiGe yellow SiH4 MFC replaced needs test 4.67/30 Tylan 9-Poly Up .57/30 Tylan 10-Nitride Up 22.24/30 Tylan 11-BPSG-LTO Up 8.18/30 Tylan 12-FGA Up Thermco 1 Up Thermco 2 Up Thermco Poly Up Thermco Nitride Down Testing Burn Box Up ZYGO up . GAAS 22 UP GAAS 23 UP SiH4 for furnaces B on line 640 changeover working well -------------- next part -------------- An HTML attachment was scrubbed... URL: From tberg at snf.stanford.edu Thu Sep 29 06:34:56 2005 From: tberg at snf.stanford.edu (Ted Berg) Date: Thu, 29 Sep 2005 06:34:56 -0700 Subject: Diffusion Morning Report 09/29/05 Message-ID: <433BED80.10207@snf.stanford.edu> Good Morning All, Looking pretty good this morning. Epi is having problems,looking into it. FGA 2 quartz is here and being installed, jungle is modified for automatic operation-sequencer is connected and functional. Thermco bank 2 is moving ahead. Everything else is OK for now. Date: 9/29/2005 THICKNESS-Change at Tube Name/Number Status Comments Tylan 1 Up Tylan 2 Up Tylan 3 Up Tylan 4 Up Tylan 5-BBr3 Up Tylan 6-POCl3 Up Tylan 7-TEOS2 Up Tylan 8-SiGe yellow SiH4 MFC replaced needs test 4.67/30 Tylan 9-Poly Up .57/30 Tylan 10-Nitride Up 22.41/30 Tylan 11-BPSG-LTO Up 8.18/30 Tylan 12-FGA Up Thermco 1 Up Thermco 2 Up Thermco Poly Up Thermco Nitride Down Testing Burn Box Up ZYGO up . GAAS 22 UP GAAS 23 UP SiH4 for furnaces B on line 630 changeover working well -------------- next part -------------- An HTML attachment was scrubbed... URL: From wuxinhua369 at vip.sina.com Thu Sep 29 22:58:57 2005 From: wuxinhua369 at vip.sina.com (=?GB2312?B?bG9uZ21pbmdodWk=?=) Date: Fri, 30 Sep 2005 13:58:57 +0800 Subject: =?GB2312?B?QW4gb3BlbiBsZXR0ZXIgdG8gQW1lcmljYW4gUHJlc2lkZW50IE1yLiBCdXNoICC+tNbCw8C5+tfczbOyvMqyz8jJ+rXEuau/qtDF?= Message-ID: <0012320870$11253478$86036373@vip.sina.com> An open letter to American President Mr. Bush ?????????????? Hello, my respectable President Mr. Bush: The fact that DuPont declined to fulfill the agreement has been presented to you for several times via president at whitehouse.gov; As a result, president at whitehouse.gov sent back three letters containing the following same contents on the behalf of Mr. President in Sep 2004:?Thank you for e-mailing President Bush. Your ideas and comments are very important to him.? My ?ideas and comments? are as follows: it is verified by Mr. Huang with adequate facts and irrefutable legal evidences that DuPont must disburse Mr. Huang patent fee, license fee or equivalent ?Utter Compensation? fee and DuPont?s persistent refusal to disburse these fees infringes upon the intellectual property rights of Mr. Huang. president at whitehouse.gov mentioned ?are very important to him.? I don?t dare to unduly surmise the meaning of ?very important? to Mr. President; However, according to my humble opinions, there exits the following ?important?: on the one hand, respectable Mr. President, the American Government led by Mr. President as well as the great American people bitterly hate the predation of the intellectual property rights of others through brazen means such as stealing, shameless acts; in contrast, DuPont is committing such brazen and shameless deals; on the other hand, the number of your country?s intellectual property rights in a variety of fields is far in excess of that of any nations in the world and suffers greatly from rights infringement. Therefore, your government always reserves no efforts in urging other nations to intensify the law enforcement strength to protect your country?s intellectual property rights. However, while your government reserves no efforts in urging the Chinese government to intensify the law enforcement strength to protect your country?s intellectual property rights and receives your ?more encouraged? praise(note), DuPont is infringing the intellectual property rights of Mr. Huang through various extremely brazen and shameless means, which constitutes an extremely bad signal to the governments and public of other nations in the world, a extremely ?good? model for current and potential thieves of intellectual property rights, an enormous damage to your government protection of your country?s intellectual property rights, and a tremendous humiliation to your country?s lofty status in the world. For the sake of the glory of the great American people and the reputation of a legion of American corporations, in order to safeguard your country?s lofty status in the world and protect the intellectual property rights of your country and other nations in the world, we humbly request you and your government to prevent DuPont?s such extremely brazen infringement and even seizure behaviors, and force DuPont to carry out it?s voluntarily promised obligations in the agreement. We firmly believe that the United State is not a country that shields and connives at rascals and the American government is not a government that shields and connives at rascals; Under the instruction of our respectable Mr. President and the American government, the rascal of DuPont shall be aware of shame and be able to turn into a normal corporation by giving up shameless behaviors. Due to the adequate evidences, the clear-cut rights and obligations of both parties of DuPont and Mr. Huang, and simple legal relations, the infringement of the intellectual property rights of Mr. Huang by DuPont can be absolutely prevented and DuPont will surely disburse Mr. Huang patent fee, license fee or equivalent ?Utter Compensation? fee as long as your government intensifies the law enforcement strength to protect intellectual property rights as well. With best regards! Authorized agent: SXF 2005.09.17.23?59 ?note? It was reported by China?s sina website on Sep 14, 2005 that China?s president Jintao Hu met with American president Bush in New York on Sep 13, and President Bush expressed his encouragement by the Chinese government actions to intensify the law enforcement strength to protect intellectual property rights. Annex: Heartfelt thanks for your reading my E-mail and your mail of attention to this matter. I would like to make some replenishment concerning the matter, for you to judge and decide. I Abstract 1. At the request of Du Pont, Mr. Huang has for 10 times submitted written technical materials to Du Pont from April 1993 to 1994, for expert group of Du Pont to conduct feasibility analysis. 2. On February 22, 1995, Dr Robert F Sklar, Technology Transfer Licensing Manager of DuPont arrived in Shanghai in China, to ?sign many agreements? with Mr. Huang. Mr. Huang insisted DuPont examines samples first before signs any agreement. However, as samples were still in the process of purification at the time, no agreements were signed then. 3. On March 28, 1995, Mr. Huang sent the first batch of samples to Du Pont by post. 4. On September 7, 1995, Mr. Huang received ?Biological Evaluation Agreement? (1995 Agreement) sent by Du Pont, requiring Mr. Huang to sign this agreement and again provide samples. Mr. Huang signed the agreement and sent second batch of samples as requested by DuPont. DuPont admit in Article 5 of the ?1995 Agreement? that Mr. Huang will be entitled to claim patent and licensing fees. DuPont states in Article 8 of the ?1995 Agreement? that Mr. Huang may not cooperate with any universities or enterprises in any form before and after signing of this agreement (for this reason, Mr. Huang has refused cooperation request of several companies). 5. On September 10, 1998, DuPont sent a letter to Mr. Huang, asking for third batch of samples. 6. In 1999, DuPont carried out a month-long insecticide screening on the third batch of samples (in fact, it has carried out weeds killing test and mould killing test in the meantime), and required to keep all these tests a secret. 7. On June 8, 2000, DuPont sent a letter saying it was not interested in samples provided by Mr. Huang, and refused to pay Mr. Huang patent and licensing fees. 8.The mail signed by DuPont on June 2th, 2005, threaten Mr.Huang ,and prevent Mr.Huang send the E-mail. ?????????????? ????????????? ?????????????????president at whitehouse.gov?????president at whitehouse.gov?? 2004?9??????????????????????Thank you for e-mailing President Bush. Your ideas and comments are very important to him.????ideas and comments????????????????????????????????????????????????????????????????????????????????president at whitehouse.gov??are very important to him.? ?very important??????????????????????????????important? ? 1.????????????????????????????????????????????????????????????????????????? 2.??????????????????????????????????????????????????????????????????????????????????????????????????????????????????????????????????????????????? ??????????????????????????????????????????????????????????????????????????????????????????????????????? ???????????????????????????????????????????????? ???????????????????????????????????????????????? ????????? ???????????????????????????????????????????????? ????????????????????????????????????????????? ???????????????????????????????????????????????? ??????????????????????????????????????????????????????????????????? ?? ??????? ??????SXF 2005.09.17.23?59 ??? ??sina?2005.09.14.????9?13??????????????????????????????????????????????????????? (??? ?? 1. ?1993?4???1994??????????????????10???????????????? ?????? 2. 1995?2?22?????????????Sklar?? ?E.I.DU PONT DE NEMOURS AND COMPANY Robert F. Sklar Ph. D. Manager,Technology Transfer Licensing)??????????????????????????????????????????????????????????? 3 1995?3?28???????????????? 4. 1995?9?7????????????BIOLOGICAL EVALUATION AGREEMENT?1995???)?????????????????????????????????????????????????1995?????5??????????????????????????????????1995?????8?????????????????????????????????????????? ???? 5. 1998?9?10?????????????????? 6 1999????????????????Insecticide Screening??????????????????????????????????????? 7. 2000?6?8?????????????????,????????????????? 8.2005.06.02. ???????????????-??????????E-mail? -------------- next part -------------- An HTML attachment was scrubbed... URL: From tberg at snf.stanford.edu Fri Sep 30 06:27:05 2005 From: tberg at snf.stanford.edu (Ted Berg) Date: Fri, 30 Sep 2005 06:27:05 -0700 Subject: Diffusion Morning Report 09/30/05 Message-ID: <433D3D29.6090608@snf.stanford.edu> Good Morning All, Looking good this morning. Ebeam operator had another problem-reset and removed cassette. Burn box cleaned this morning. FGA2 tube coming along-waiting expert feedback. THermco bank 2 coming along fine. Everything else looks OK for now. Date: 9/30/2005 THICKNESS-Change at Tube Name/Number Status Comments Tylan 1 Up Tylan 2 Up Tylan 3 Up Tylan 4 Up Tylan 5-BBr3 Up Tylan 6-POCl3 Up Tylan 7-TEOS2 Up Tylan 8-SiGe yellow SiH4 MFC replaced needs test 4.67/30 Tylan 9-Poly Up .57/30 Tylan 10-Nitride Up 22.55/30 Tylan 11-BPSG-LTO Up 10.83/30 Tylan 12-FGA Up Thermco 1 Up Thermco 2 Up Thermco Poly Up Thermco Nitride Down Testing Burn Box Up ZYGO up . GAAS 22 UP GAAS 23 UP SiH4 for furnaces B on line 630 changeover working well -------------- next part -------------- An HTML attachment was scrubbed... URL: From nanotech at nsti.org Fri Sep 30 06:20:18 2005 From: nanotech at nsti.org (NSTI) Date: Fri, 30 Sep 2005 06:20:18 -0700 Subject: Nano Summit & Course Deadline Today Message-ID: An HTML attachment was scrubbed... URL: