Diffusion Morning Report 05/03/06
Ted Berg
tberg at snf.stanford.edu
Wed May 3 07:56:49 PDT 2006
Good Morning All,
Looking good this morning. Epi HCl crossed over. TEOS pump is bad
and out for repair-approximately 1.5 weeks. Thermco2 back up after
removing burnt wipe. Everything else looks OK for now.
Diffusion
Date: 5/3/06 THICKNESS-Change at
Tube Name/Number Status Comments
Tylan 1 Up
Tylan 2 Up
Tylan 3 Up
Tylan 4 Up
Tylan 5-BBr3 Up
Tylan 6-POCl3 Up
Tylan 7-TEOS2 Down Pump out for repair 20.43/30
Tylan 8-SiGe Up 29.39/30
Tylan 9-Poly Up 2.73/30
Tylan 10-Nitride Up 24.51/30
Tylan 11-BPSG-LTO up 5.12/30
Tylan 12-FGA Up
Thermco 1 Up
Thermco 2 Up
Thermco Poly Up
Thermco Nitride Down Testing
Epi yellow possible higher leak rate
HCl Changed today
Burn Box Up
ZYGO up
GAAS 22 UP
GAAS 23 up
SiH4 for furnaces A on line 575 psi changeover working well
-------------- next part --------------
An HTML attachment was scrubbed...
URL: <http://snf.stanford.edu/pipermail/diffusion/attachments/20060503/400ad1c4/attachment.html>
More information about the diffusion
mailing list