Diffusion Morning Report 03/06/08
Ted Berg
tberg at stanford.edu
Thu Mar 6 06:12:08 PST 2008
Good Morning All,
Looking good this morning Tylans1 and 2 have boat issues- working on
them. LTO is back together leak checking. SiGe temp cal. No other issues
at this time.
Date: 3/6/08 THICKNESS-Change at
Tube Name/Number Status
Tylan 1 down i/o error
Tylan 2 up
Tylan 3 up
Tylan 4 up
Tylan 5-BBr3 up
Tylan 6-POCl3 up
Tylan 7-TEOS2 up 2.71/30
Tylan 8-SiGe up temp cal-600 done working on 650 10.63/30
Tylan 9-Poly up 4.2/30
Tylan 10-Nitride up 4.71/30
Tylan 11-LTO down Scheduled pull and clean 0/30
Tylan 12-FGA up
Thermco 1 up
Thermco 2 up
Thermco 3 future
Thermco4 future
Thermco Poly1 up
Thermco Poly2 up
Thermco Nitride1 up
Thermco Nitride2 future
TEL Spa up
Burn Box Up
Ebeam up
ZYGO up
FGA2 up
SiH4 for furnaces up B on line 370 psi changeover working well
-------------- next part --------------
An HTML attachment was scrubbed...
URL: <http://snf.stanford.edu/pipermail/diffusion/attachments/20080306/f5e35cc4/attachment.html>
More information about the diffusion
mailing list