Diffusion Morning Report 01/20/10
Ted Berg
tberg at stanford.edu
Wed Jan 20 07:04:16 PST 2010
Good Morning All,
Looking good this morning . Most of the tools are back up LPs are
waiting testing. Ebeam is coming back up. No other issues at this time.
Date: 1//2010 THICKNESS-Change at
Tube Name/Number Status
Tylan 1 up
Tylan 2 up
Tylan 3 up
Tylan 4 up
Tylan 5-BBr3 up
Tylan 6-POCl3 up
Tylan 7-TEOS2 up 1.44/30
Tylan 8-SiGe yellow needs test 7.45/30
Tylan 9-Poly yellow needs test 6.16/30
Tylan 10-Nitride yellow needs test 22.55/30
Tylan 11-LTO up 24.06/30
Tylan 12-FGA up
Thermco 1 up
Thermco 2 up
Thermco 3 future
Thermco4 future
Thermco Poly1 yellow needs test
Thermco Poly2 yellow needs test
Thermco Nitride1 yellow uniformity issues ?
Thermco bpsg future testing for qual
TEL Spa up
Burn Box up
Ebeam down power fail
ZYGO up
FGA2 up
SiH4 for furnaces A on line 520 psi changeover working well
-------------- next part --------------
An HTML attachment was scrubbed...
URL: <http://snf.stanford.edu/pipermail/diffusion/attachments/20100120/026bcf87/attachment.html>
More information about the diffusion
mailing list