Diffusion Morning Report 06/28/11
Ted Berg
tberg at stanford.edu
Tue Jun 28 07:46:23 PDT 2011
Good Morning all,
Looking good this morning. Dome for epi is installed and cycle
purging(we borrowed one from the new kit). TEOS had pressure
issues-checking it out. Thermco 2 no TLC flow. Thermco 1 low growth. CDA
to the fab was off this morning so some tools may have been down. No
other issues at this time.
Date: 6/28/11 THICKNESS-Change at Priority
Tube Name/Number Status
Tylan 1 *up* ** ** ** **
Tylan 2 *up* ** ** ** **
Tylan 3 *up* ** ** ** **
Tylan 4 *up* ** ** ** **
Tylan 5-BBr3 *up* ** ** ** **
Tylan 6-POCl3 *up* ** ** ** **
Tylan 7-TEOS2 *yellow* *pressure issues* *10.14/30* ** *2*
Tylan 8-SiGe *up* ** *1.94/30* ** **
Tylan 9-Poly *up* ** *22.3/30* ** **
Tylan 10-Nitride *up* ** *16.51/30* ** **
Tylan 11-LTO *up* ** *10.4/30* ** **
Tylan 12-FGA *up* ** ** ** **
Thermco 1 *yellow* *low growth rate* ** ** **
Thermco 2 *yellow* *no tlc flow* ** ** **
Thermco 3 *future* ** ** ** **
Thermco4 *future* ** ** ** **
Thermco Poly1 *up* *
* ** ** **
*up* ** ** ** **
Thermco Nitride1 *yellow* *pressure issues* ** ** **
Thermco bpsg *up* ** ** ** **
AMAT Epi *down* *dome installed-cycle purging* ** ** *1*
TEL Spa *up* ** ** ** **
Burn Box *up* ** ** ** **
Ebeam *down* *cryo compresssor dead* ** ** **
ZYGO *up* *
* ** ** **
FGA2 *up* ** ** ** **
SiH4 for furnaces ** *B on line pressure 938 psi* *changeover working
well* ** **
-------------- next part --------------
An HTML attachment was scrubbed...
URL: <http://snf.stanford.edu/pipermail/diffusion/attachments/20110628/e54fd4e0/attachment.html>
More information about the diffusion
mailing list