Epi Reactor Lower Dome update 11/23/11
maurice stevens
maurice at stanford.edu
Wed Nov 23 16:07:41 PST 2011
We had a very good day!
We will installed the upper quartz and dome, confirmed correct wafer
placement in process chamber and pumped down system.
System is now baking out. I will come in on Friday to etch the chamber,
get temperature readings and run silicon depositions.
We will update on you all on Friday.
-m
On 11/22/2011 4:32 PM, maurice stevens wrote:
> Hi All,
>
> We received the lower dome midday yesterday and were able to removed
> the upper dome and all the upper quartz.
>
> Today we (1) pulled the lower lamps, rotation assembly and the lower
> dome (2) cleaned the upper/lower flanges, cleared inner rotation of
> broken wafers/quartz (3) re-installed lower dome, lower lamps and
> rotation assembly.
>
> Tomorrow we will install the upper quartz and dome, calibrate wafer
> placement in process chamber, pump down system and finally (if
> everything goes well) start the bake out.
>
>
--
maurice at stanford.edu
Maurice Stevens
Stanford Nanofabrication Facility
CIS Room 142, Mail Code 4070
Stanford, CA 94305
P. (650)725-3660
F. (650)725.6278