Etch Group - Morning Equipment Status Report 9:00 am
Astrisk (*) = equipment up & ready for use
AG4108 * each user needs to verify Config values
values can change if power-cycled
AMTetcher Shutdown Arcing on trays & trays are loos
Drytek1 Shutdown CF4 repair in progress
Drytek2 *
Drytek4 Problem Standby light is not working
Gasonics Shutdown waiting for process recipe(s) to be
approved, Jim McVittie
Lampoly *
Lamsi NOT installed
Matrix *
MRC Problem SF6 flow sometimes unstable & chamber pressure
varies with some STSetch process operation
P5000etch Problem Ch A backsid Helium flow faults
Pquest *
Prometrix *
RTAag *
RTAgaas NOT installed
STSetch *
Wafersaw *