Etch Group morning equipment status: 5/16/2005
Elmer Enriquez
eenriquez at snf.stanford.edu
Mon May 16 08:09:00 PDT 2005
* Etch Group - Morning Equipment Status Report
*
*5/16/2005 8:15 am*
*Etch Equipment :*
Equipment
Status
Comments
AMTetcher
UP
Need to clean the viewport
Drytek 1
UP
Drytek 2
UP
Drytek 4
UP
Gasonics
UP
Lampoly
Down
HBr is not available. HBr gas panel leak.
* Completed gas panel re-build.
* Completed HBr sensor test
* Gas panel is installed
* HBr cylinder is installed
* Passed 24 hour pressure test
----------------------------------------------------
* Need to replace gas sensors with the proper sensors. Scheduled to
be installed on Tuesday.
Lam Si
N/A
Not installed
Matrix
UP
MRC
UP
P5000
Problem
Ch. C is down ; HBr is not available. See Lampoly comments.
PQuest
UP
STSetcher
UP
STSetcher 2
Not Released
Process start-up.
*
Miscellaneous Equipment:*
Equipment
Status
Comments
AG 4108
UP
Oxication tray installed
AG 4100
N/A
Start-up. Waiting for the installation permit.
* Cycled 50 wafers running an N2 recipe.
* Completed pyrometer calibration.
* Completed exhaust connection.
* Completed lamp calibration.
* All calibrations have been completed .
-----------------------------------------------------------------------------------------------------------------
* Installed a temporary oxygen cylinder.
* Copied anneal and oxidation recipes from the AG4108
RTAag
UP
RTAGaAs
UP
Wafersaw
UP