Shutdown headway2 SNF 2009-08-18 07:56:07: Monthly Preventive Maintenance In progress......
vilanova at snf.stanford.edu
vilanova at snf.stanford.edu
Tue Aug 18 10:29:18 PDT 2009
Monthly Preventive Maintenance Completed.
Cleaned Fittings ,Shaft ,Spolenoid ,Secondary Recovery Flask
Cleaned bench , Tested, Working Like A Champ!
Ok to use.