Shutdown headway2 SNF 2009-10-15 08:57:04: Monthly Preventive Maintenance In progress......

vilanova at snf.stanford.edu vilanova at snf.stanford.edu
Thu Oct 15 10:46:07 PDT 2009


Monthly Preventive Maintenance Completed.
Cleaned vacuum Lines, Solenoid,Shaft 
Spindle Bearings Fittings and secondary catch cup
replaced Seal Gasket, Replaced all of the CHucks Orings and
cleaned Chucks, Cleaned Bench Inside+Outside




More information about the headway2-pcs mailing list