Painting schedule
Dick Crane
rcrane at snf.stanford.edu
Tue Feb 18 17:17:22 PST 2003
CIS/CISX building dwellers,
Here is the latest schedule for the building painting/detailing work.
First Floor Common Areas of CIS (including lobby restrooms)
Start Date: Monday, February 10
Completion date: Tuesday, February 18
Second Floor and Stairways of CIS
Start Date: Tuesday, February 18
Completion Date: Friday, February 21
West stairs: Friday, February 21
East stairs: Monday, February 24
CIS115: Thursday, February 20, 0630-1030
CIS201: Monday, February 24, 0630-1030
First Floor Common Areas of CISX
Start Date: Monday, February 24
Scope
Areas to be painted include:
Common areas outside offices and conference rooms
Stairways (except the maintenance stairway)
SNF wall (partial)
All columns
Door frames no doors
Drywall repair in front entry
Lobby desk (after repair)
Hours: 6:30-3:30 and weekends not Monday, 2/17/03
Thanks for your cooperation,
Dick Crane