WB silicide Move

tberg tberg at snf.stanford.edu
Mon Sep 27 09:42:32 PDT 2004


Hello all,
    As part of the move to 6" capability the WBsilicide wet bench will 
be moved in approximately 2 weeks.  This will allow bank 4 to be moved 
out and the other Thermco bank to be moved in WBsilicide will be down 
for approximately 2 weeks assuming permit issues are satisfied.  Please 
let Dick Crane or myself know if there are any problems or issues.  
Process is working on an alternative clean area while this happens. 
Thanks ted