Fwd: BioE+ChE Construction Update - Week of April 16th
Kenny Green
kennygee at stanford.edu
Fri Apr 13 13:06:12 PDT 2012
Please find attached the update for next week.
Changes from last week include:
* Shotcrete operations will resume work on the North side of the site
in the light well.
* East portions of slab on grade in the basement and subbasement are
now being poured next week.
* Major pours next week will be for slab on grade on Monday (approx. 9
trucks) and Friday (approx. 15 trucks).
Have a great weekend.
Chris Virgilio
Whiting-Turner Contracting Co.
4000 Via Ortega
Stanford, CA 94305
o. 925.271.6596
c. 925.580.4554
-------------- next part --------------
An HTML attachment was scrubbed...
URL: <http://snf.stanford.edu/pipermail/labmembers/attachments/20120413/81aa8d4c/attachment.html>
-------------- next part --------------
A non-text attachment was scrubbed...
Name: 2012.04.16 - Weekly Update BioE + ChE..pdf
Type: application/octet-stream
Size: 1745037 bytes
Desc: not available
URL: <http://snf.stanford.edu/pipermail/labmembers/attachments/20120413/81aa8d4c/attachment.obj>
More information about the labmembers
mailing list