Photolithography Area Status
Tuesday , February 01, 2011
General Information / Lab Activities
Temp/Humidity/Airflow problem in aisle L-102(SVG Coat/Develop aisle) due to transfer fan problem.
Exposure Tools
Status
Comments
Priority
ASML Stepper - Converting to 6" until tomorrow 2/2/2011
UP
EVAlign
UP
EVAlign2
UP
EVG-Imprint
UP
Karl Suss 1
UP
Karl Suss 2
UP
Manual Coaters
Status
EVGSpraycoat
UP
Headway
UP
Laurel
UP
Coaters
Process Status
SVGCoat
3612 Process
Up
220-3 Process
Up
220-7 Process
Problem
Optimizing Process
1
SVGCoat2
3612 Process
Up
955-0.7 Process
Up
3617 Process
Up
Developers
Status
SVGDEV
UP
SVGDEV2
UP
Ovens / Hotplates
Status
BLUEM
UP
Blue M 90 C.
UP
Blue M 110 C
UP
Blue M 150 C
UP
Fusion
DOWN
Hotplate experiments
UV-Cure
UP
White-Oven
UP
YES Vapor Prime
UP
Hotplates-
Laurel-left
UP
Laurel- right
UP
Headway
UP
Torrey Pines- left
UP
90 Deg C
UP
115 Deg C
UP
Torrey Pines- Right
UP
Metrology/Inspection
Status
Alpha-Step 500
UP
Nanospec 2-Litho
UP
Nanospec 1-Etch
UP
P2 Profiler
PROBLEM
-11 stage error
4
Microscpoes-
#1 Leica/Analytical
UP
#2 Ergolux/Drytek2
UP
#3 Olympus/Litho
UP
#4 Nikon Optiphot/Litho
UP
#5 Nikon/Litho
UP
#6 Leitz/Bosch
UP
#7 Leitz/Diffusion
UP
#8 Olympus/Litho
UP
#9 Olympus/Litho
UP
Miscellaneous
Status
EVBond
PROBLEM
Left flag did not pull
3
KSBonder
PROBLEM
Leaking nitrogen hose
5
KSCoat
UP
Litho SRD
UP
Mask Cleaner
DOWN
Water leak, Waiting for parts
2