From fmwang at snf.stanford.edu Wed Dec 1 03:27:21 2010 From: fmwang at snf.stanford.edu (fmwang at snf.stanford.edu) Date: Wed, 1 Dec 2010 03:27:21 -0800 Subject: Problem metalica SNF 2010-12-01 03:27:21: Plasma didn't strike Message-ID: The interlock is on without plasma. From jperez at snf.stanford.edu Fri Dec 3 07:05:37 2010 From: jperez at snf.stanford.edu (jperez at snf.stanford.edu) Date: Fri, 3 Dec 2010 07:05:37 -0800 Subject: Problem metalica SNF 2010-12-01 03:27:21: Plasma didn't strike Message-ID: Set-up must of been the problem, because others have used Metalica for two days without reporting a problem. From sgchong at snf.stanford.edu Fri Dec 10 16:21:51 2010 From: sgchong at snf.stanford.edu (sgchong at snf.stanford.edu) Date: Fri, 10 Dec 2010 16:21:51 -0800 Subject: Comment metalica SNF 2010-12-10 16:21:50: One of the Ti targets reaching limit Message-ID: One of the Ti targets is reaching its limit (0.020 inch). From jackson at snf.stanford.edu Thu Dec 16 02:05:13 2010 From: jackson at snf.stanford.edu (jackson at snf.stanford.edu) Date: Thu, 16 Dec 2010 02:05:13 -0800 Subject: Problem metalica SNF 2010-12-16 02:05:12: cryo power off Message-ID: After start of deposition, had cryo power off problem. could not continure depositions. From jperez at snf.stanford.edu Thu Dec 16 07:07:40 2010 From: jperez at snf.stanford.edu (jperez at snf.stanford.edu) Date: Thu, 16 Dec 2010 07:07:40 -0800 Subject: Comment metalica SNF 2010-12-10 16:21:50: One of the Ti targets reaching limit Message-ID: replaced. From jperez at snf.stanford.edu Thu Dec 16 07:22:30 2010 From: jperez at snf.stanford.edu (jperez at snf.stanford.edu) Date: Thu, 16 Dec 2010 07:22:30 -0800 Subject: Shutdown metalica SNF 2010-12-16 07:22:30: down for rebuilt of shaft that lifts the bell jar Message-ID: