Comment raith SNF 2007-01-16 11:33:52: functional test system - schedule resumes at 15:00

jwc at snf.stanford.edu jwc at snf.stanford.edu
Tue Jan 16 11:33:53 PST 2007


Morning UPDATE:
1. Water flow failure alarm brought the system down and it went into standby mode to ensure gun vacuum integrity.  Partial vent of SYS chamber but not the GUN section.  Now pumping down.
2. Will check out the chiller flow and temperature,  load lock functionality.
3. NO stage piezo leveling post control:
A problem was reported by system at login with IEE-488 interface to stage piezo post. 
	- RESOLVED -- RESET  WIN OS to resolved communications buss error.
CORAL SCHEDULE RESUMES AT 15:00 THIS AFTERNOON.
Good Day,
James Conway