RAITH Offline for the Holidays!! Plan to return to service January 5 for RAITH Champions and Jan 10th for All other users. SHUT DOWN AND START UP PLAN.
James Conway
jwc at snf.stanford.edu
Mon Dec 18 14:42:08 PST 2006
*Happy Holiday Greetings to the Raith Community:
The Year in Review:
*
Well it was a wild ride for the RAITH community this last year with a
great run of uptime through the first two thirds of the year; followed
by several upsets resulting in significant downtime during the later
months of 2006. However All-in-All the performance of the system has
been superb and well within the system specifications.
2006 also saw the RAITH community grow to almost 150 members as some
older Users migrating off the system as they graduate and a very large
group of new users coming onto the system late this year. In November
alone we had 10 new users start on the system with only a few load lock
errors encountered.
By my count I have now trained more than 160 users on the RAITH system
to date at Stanford University.
In 2006 we also observed the first RIE etched EBL features coming off
the RAITH system with line width features below 10 nm. In fact several
structures were found for Single Pixel Lines with line widths, and and
single shot Dot diameters, in the 5 to 7 nm range. This is world class
Electron Beam Lithography results and everyone working in the SNF Ebeam
Lab should feel a sense of being a participant in this effort. Good Job
to everyone!
*Special Thanks to the following People and Groups:
*
I would like to thank the entire RAITH Community, especially the many
RAITH Champions, for your efforts above and beyond the call of duty to
keep the system up, help the many new Users come up to speed, and always
being there to lend a hand when it was needed. I would also like to
thank all the members of Raith USA Inc. and RAITH GmbH in Dortmund,
Germany for their constant encouragement and support as we have moved
through several software upgrades and for responding to problems and
support when we have needed it. Thanks also to Mike Santomango with Carl
Zeiss SMT for many service responses and timely phone calls.
Finally a special thanks to Dick Crane, Ted Berg, and the entire
maintenance group whom have worked tirelessly behind the scenes ensuring
the facility stays up so our systems can also maintain uptime. Dick is
retiring next month so say 'hello' the next time you see him in passing
and _Thank Him_ before he leaves at the end of January.
Finally thanks to Mary Tang for her patience and gentle leadership; to
Paul Jerabek and Ted Berg for continuing to take on and tame the Hitachi
HL-700-F so I can concentrate on the RAITH. Finally Many kudos's also go
out to all of our SNF Process Staff whom maintain a lab that we can get
our work done with the highest quality.
Overall I think 2006 was a great year! I look forward to the same level
of engagement with all users on the RAITH tool in 2007.
My hope in 2007 is to push the limits of what we can do on the RAITH
system, improve the metrology and imaging equipment available to users
working in the SNF Cleanroom and Ebeam Lab all the while creating
pathways to everyone's success in their research in nanotechnology at
the Stanford Nanofabrication Facility.
To each and every one of you, and to your families, a very Joyous
Holiday Season and a Happy New Year!
Safe Travels where ever you go,
James Conway
Ebeam Lab
Stanford Nanofabrication Facility
_*Schedule for Shutdown and Startup:*_
12-18-2006 12:00 Noon Lab and RAITH system are shut down and in Bake Out
for the Holiday
NO USER ACCESS TO THE CLEAN ROOM.
01-04-2007 10 - 15:00 hours ZEISS Field Service comes in and brings the
FE-GUN back on line.
NO USER ACCESS TO THE SYSTEM.
01-04-2007 10 - 15:00 hours to 15:00 01-05-2007: FE_GUN run in and
conditioning.
01-05-2007 10 AM Zeiss Field Service performs Electron Optics card
adjustments and performs a preliminary system check out.
NO USER ACCESS TO THE SYSTEM.
01-05-2007 15:00 to 11:00 01-08-2007. Possible access to the RAITH
system if handed off for 'testing' by ZEISS Field Service.
_*RAITH Champion user access ONLY -- unless escorted by a RAITH Champion.
*_01-08-2007 12:00 to 01-09-2005 1800 hours SYSTEM off line to users for
RAITH USA Inc. Field Service for some preventative service on the
cooling section and Laser Interferometer Stage and Loader of the RAITH
system. This will be followed by the RAITH Qualification for Performance
as we have done in the past.
There may exist some periods over each evening when the RAITH may be
available by Users to assist us in performance testing. We will do our
best to return the system to all Users as soon as possible during this
week once the system is qualified.
_* JWC's Request for 'Safe and Sane' *__*Coral *__*reservations:
*_To avoid massive jumbling and consequent grumblings during the start
up of the RAITH system in January I am requesting you:
* Please do not make reservations on CORAL for any time before
January 5, 2007 at 15:00 hours. Likely there will be no system
access until after this time at the very best.
* Only RAITH Champions may make Coral reservations for any time
*before* WED. January 10, 2007 at 12:00 Noon. The Coral schedule
will begin in earnest for all users at that time.
* All Users are encouraged to 'Share the Ride' and optimize the
operations time by working closely with the User before and after
your session to hand off the system smoothly. This is in order to
allow everyone a chance to come back onto the system in the first
two weeks of operations in 2007! Users should start timing their
writes to avoid idle time at the end of their reservations time
slots. Please strive to improve the throughput of the system now
that we have so many users on the tool!
*Thank you for your support!
** **James Conway 415-412-4825 cell...
* I will be returning to SNF mid to late morning Monday 01-08-2007.
I will be unavailable except for emergencies from December 26, 2006 -
January 2, 2007.
-------------- next part --------------
An HTML attachment was scrubbed...
URL: <http://snf.stanford.edu/pipermail/raith/attachments/20061218/ac278dfb/attachment.html>
-------------- next part --------------
A non-text attachment was scrubbed...
Name: xmooselights.gif
Type: image/gif
Size: 45777 bytes
Desc: not available
URL: <http://snf.stanford.edu/pipermail/raith/attachments/20061218/ac278dfb/attachment.gif>
More information about the raith
mailing list