updates are coming pretty fast now.  from the sensor tests yesterday
everything on the fiji is good to go with the exception of the ozone sensor.
 it creates an open circuit upon detection and ted berg and the snf
maintenance gang would prefer an closed circuit.  a new ozone sensor is
being sent and will be installed next week with the inspection scheduled as
soon after installation of the ozone sensor as possible.  upon successful
inspection the acceptance test will be performed and we are still on target
and cautiously optimistic for a June start up.

please let me know if you have any questions.

j

On Wed, Jun 8, 2011 at 9:59 AM, J Provine <jprovine at stanford.edu> wrote:

> hello fiji enthusiasts,
> a representative from cambridge nanotech was out at stanford a few weeks
> ago to finish setting up the fiji.  everything checked out fine and ted berg
> finished the last few interlocks earlier this week.  there was a pre-test of
> the sensors this morning and the county inspection is scheduled for early
> next week.  i'm currently scheduling the acceptance test visit from
> cambridge nanotech to happen as soon as after the county inspection as
> possible.
>
> we are still on target for the machine to begin test depositions in
> mid-June, depending on rapidity of the various schedulings.
> j
>
-------------- next part --------------
An HTML attachment was scrubbed...
URL: <http://snf.stanford.edu/pipermail/savannah/attachments/20110610/248a86b9/attachment.html>


More information about the savannah mailing list