Tool shutdown 8/17-8/26
Dick Crane
rcrane at snf.stanford.edu
Tue Jul 26 11:43:19 PDT 2005
Fab users,
STS (dep) and ag4108 disruption alert, August 17, 2005, one and a half
weeks duration.
The ag4108 and the STS pecvd tools will be off-line for processes
requiring ammonia gas for one and a half weeks starting around August
17. I believe the one and a half weeks quoted is generous and the actual
time may be less than 1 week. This schedule allows permitting and
inspection activities to occur at the same time as needed for a
scheduled furnace shutdown, thus minimizing overall fab downtime.
Please plan ahead for your tool needs.
Thank you for your patience and support,
Dick
Details:
The NH3 gas cabinet supplies both the ag4108 and STS tools. NH3 gas
lines are being extended to the ag4100 (new install) and the ALD
(rebuilt spectrum2). Since the toxic and house gases are regulated by
Santa Clara County Building and Environmental Departments, all work must
be tested and inspected according to their timetable. We will complete
as much preliminary work as possible prior to shutting down gases.
-------------- next part --------------
An HTML attachment was scrubbed...
URL: <http://snf.stanford.edu/pipermail/sts/attachments/20050726/8eb5b787/attachment.html>
More information about the sts
mailing list