Comment stsetch2 SNF 2012-03-08 11:30:45: Update
eenriquez at snf.stanford.edu
eenriquez at snf.stanford.edu
Thu Mar 8 11:30:46 PST 2012
Defective part appears to be the wafer lift bellows. The lead time is 3-4 weeks. Best estimate for the system to be available is 4/9.