Shutdown teos2 SNF 2009-09-15 06:11:38: leaks

seymour at snf.stanford.edu seymour at snf.stanford.edu
Wed Sep 16 11:30:04 PDT 2009


Pulled the tube and replaced all the orings. reassembled sustem and did leak check. turned on element breaker and when hot did another leak check. Base good at 19 mT, ROR was 5 mT/min. 