Bank 2 going down for TEOS conversion
beckwith at cis.Stanford.EDU
beckwith at cis.Stanford.EDU
Fri Dec 5 17:03:40 PST 2003
Hi Ted:
I will need tylan5 and tylan6 on Thursday, Dec. 11. If all goes
well on Thursay, I will not need the tubes for a long time after
that (at least not until we come back in Jan.).
Thanks for asking!
Sharleen
On Fri, 5 Dec 2003, ted berg wrote:
> Hello all,
> This bank will be going down for approximately 2 weeks to change the
> scavenger and element for TEOS. This could happen as early as the 16th
> of this month.
> If anyone has major projects that will be affected please let me know so
> we can schedule accordingly. Thanks,ted
>
>
More information about the tylan6
mailing list